Mokokchung Nagaland

Mokokchung Division Under Tey Power Shutdown Hoishey

October 18, 2023 : Department of Power, Office of Executive Engineer Transmission Division para toh hoiley informed kurishey, sob manu khan ke, ki, itu Vegetation Clearance 132kV aru 66kV Transmission Lines nimitey, Transmission Division Mokokchung under tey, 23rd  Oct 2023 para 18th  November 2023  tak scheduled asey. Itu laga regard tey, tatey toh hoiley pura puri shut down thakibo, power laga, 08:00 AM para 4:00 PM hudai, itu kaam toh bhal para khotom kuriboley pariboley smooth para, eku dikdar nahoi kena. Itu exercise toh hoiley kuriboley laga hoishey, thik thak power supply dibo pariboley aru unwarranted disruption laga supply toh avoid kuriboley.

Itu department para appeal kurishey public khan ke, itu affected thaka area tey, cooperate kuriboley aru itu inconvenience toh bear kuriboley, itu shutdown laga homoi tey.

Sl. No.Schedule DateFeedersAffected area under Shut Down
123rd Oct –  28th Oct, 202366kV Mokokchung- Zunheboto Transmission LineZunheboto District.
230th  Oct – 3rd Nov, 2023132kV Mokokchung- Doyang Transmission Line 
306th Nov – 11th Nov, 202366kV Mokokchung-Tuli 66 kV Tuli-N/Mora 66kV N/Mora-Tizit 66kV Tizit-Mon Transmission LineChangtongya Sub-Div, Tuli Sub-Div, Longleng & Mon District.
413th Nov – 18th Nov, 2023132kV Mokokchung-Mariani Transmission Line